Wednesday, 29 May 2013

Mon - Wed, May 27 - 29

Putting stone work above the canopy
The masonry boss at work


Hallway to the meeting room gets drywall on the ceiling



Ceiling is done

Basement stairs are in

Cold air return pipes for the sanctuary


Saturday, 25 May 2013

Fri, May 24

New door and addition to the consistory room

White line on right wall is where the room ended before

Stair well to the basement

Framing in the basement walls

Outside brick work continues

Friday, 24 May 2013

Tues - Thurs, May 21 - 23

Working on the roof of the canopy


Brick work begins

Stonework under the windows

Old brick is reused around and above the windows
Nearing the top
Double door opening from the new hallway to the meeting room
Opening for cold air return from the sanctuary
Inside the consistory room
-space is made for a counter with sink, and a small closet
 


Drains, vents, and heating above the handicap washroom


Framing from existing foyer to addition
-whiter line on brick is where the outside wall was









Saturday, 18 May 2013

Thurs & Fri, May 16 & 17




Removing the old furnace and heating pipes
The electricians have been busy all week too!
Another electrician at work



The new heating pipe from the basement (front right)
to the sanctuary
Pouring the basement floor
Pouring the floor for the new washrooms
Concrete floor being put in the new washrooms

Thursday, 16 May 2013

Wed May 15

Roofing continues on the front side of the church
Bringing more bundles - wow, that's a lot of shingles!




Insulating the roof drain pipes

More heating pipes are installed
Hardware arrives for the inside doors


Tues, May 14


Shingling of the entire roof begins, both the existing and the addition
 
As the bundles of shingles are still being boomed up, the first ones are already being nailed on



The roof gets a new colour - Brandywine Dusk




Working on the north side of the meeting room






A good start


Moving on to the roof of the addition



Here you can see the change of colour - the sanctuary (on right) being the old colour
Work in the top of the new foyer also continues
Bulkheads and end peak are drywalled
Bulkheads are framed in around the heating ducts in the nurseries

Putting plumbing pipes in for handicap washroom

Saturday, 11 May 2013

Fri & Sat, May 10 & 11


Looking from inside the new foyer towards the back entrance

Looking from the back entrance into the new addition to the foyer
The wall and door at the end are temporary
(sanctuary is to the right)

Installation of in-floor heating in basement


In-floor heating hoses