Tues, May 14


Shingling of the entire roof begins, both the existing and the addition
 
As the bundles of shingles are still being boomed up, the first ones are already being nailed on



The roof gets a new colour - Brandywine Dusk




Working on the north side of the meeting room






A good start


Moving on to the roof of the addition



Here you can see the change of colour - the sanctuary (on right) being the old colour
Work in the top of the new foyer also continues
Bulkheads and end peak are drywalled
Bulkheads are framed in around the heating ducts in the nurseries

Putting plumbing pipes in for handicap washroom

Saturday, 11 May 2013

Fri & Sat, May 10 & 11


Looking from inside the new foyer towards the back entrance

Looking from the back entrance into the new addition to the foyer
The wall and door at the end are temporary
(sanctuary is to the right)

Installation of in-floor heating in basement


In-floor heating hoses