Wednesday, 24 April 2013

Thurs. & Fri. April 18 & 19

The framing begins
Building the first wall
The first wall is ready to be set up
The first outside wall is up



A tight fit - end wall by the consistory room
Most of the outside walls are framed
Framing against an existing wall (beside kitchen window)


New washroom - getting ready to install plumbing
Drain pipes laid out





Digging further for more drains


Working on the new electrical panel




Wed. April 17

Setting forms for concrete piers for outside pillars at rear entrance


Pouring piers for outside pillars


Underground piping for geothermal


Burying geothermal piping